Russia Infrastructure Tracker.

Progress, deadlines and site footage of Russia's major construction projects — culture and tourism clusters, roads and railways, energy and industry, stadiums and city projects. Based on primary sources, updated every Monday.

45
Projects tracked
26
Under construction
17
Delayed > 12 months
15
Operational / completed
9
Updated this week
Last update: 30 Oct 2026Updated every Monday

What moved this week

The tracker went live on 30 Oct 2026. The first weekly update follows on Monday, 2 Nov 2026.

Map

Zoom with the buttons, mouse wheel or two fingers; drag to move. Click a pin for the project record.
MoscowSt PetersburgKazanYekaterinburgNovosibirskIrkutskYakutskVladivostokMurmansk
Hover briefly or hold Ctrl to zoom with the wheel

Sectors

Culture & Tourism
Transport
Energy & Industry
Cities & Sport
Pulsing pins: new primary-source update this week.

Plan vs. reality

First officially announced completion date (hollow) against the current official date (filled). Dotted line: today.

All projects

45 projects

Every figure carries its date and primary source. Open a record for the deadline history, site footage and sources.

Kemerovo on the Tom river (2013)Photo: Mr Hicks46 / Wikimedia Commons, CC BY-SA 2.078.5%Culture & TourismUpdated 27 Oct 2026
Kemerovo Oblast (Kuzbass)

Siberian Cultural and Educational Cluster (museum-theatre complex), Kemerovo

Сибирский культурно-образовательный кластер (музейно-театральный комплекс), Кемерово
Partially operationalDelayed > 12 months
Construction progress78.5%
Original deadline
Dec 2023
Current deadline
2027
+4 yrs
Latest · 27 Oct 2026On 27 October 2026 Deputy PM Khusnullin inspected the site with Governor Seredyuk: readiness 'more than 70%', about 2,000 workers, first visitors expected next year; all other objects of the cluster are completed. (Marat Khusnullin, Deputy Prime Minister (Telegram))
Full record

Project

One of the presidential cultural clusters: 12 objects, of which the last one under construction is a 155,000 m² museum-theatre complex on the Iskitimka river combining a Mariinsky Theatre branch (main hall 950 seats), a Russian Museum branch and the Kuzbass Arts Centre under one atrium. The educational part (choreography academy, music school, RGISI campus, depository, housing) is already in use.

Next milestone

Commissioning of the museum-theatre complex (Mariinsky and Russian Museum branches, Kuzbass Arts Centre) (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Moscow

Simonovskaya and Krutitskaya embankments (Moscow)

Реконструкция Симоновской и Крутицкой набережных (Москва)
Partially operationalDelayed > 12 months
Construction progressNo official progress figure
Original deadline
2023
Current deadline
2027
+4 yrs
Latest · 4 Sep 2026On 4 Sep 2026 Mayor Sobyanin opened the rebuilt Krutitskaya embankment and the first section of the new Simonovskaya embankment from Novospassky bridge to the Torpedo stadium, adding 2.2 km to Moscow's continuous embankment line, including an underpass and a riverside pedestrian and cycle zone over 1 km long. (Sergei Sobyanin, Mayor of Moscow (Telegram))
Full record

Project

About 6 km of new and rebuilt embankment roads with 2-3 lanes per direction on the left bank of the Moskva river from Novospassky bridge past the Torpedo stadium and the former ZIL site to the Third Ring Road, with bank reinforcement and riverside promenades and cycle paths.

Next milestone

Landscaping of the 500 m area next to Krutitskaya embankment and construction of the second Simonovskaya section from the River Sky residential complex to the Third Ring Road; full completion planned for 2027.

Deadline history

Kaliningrad Oblast

Cultural, Educational and Museum Complex on Oktyabrsky Island, Kaliningrad

Культурно-образовательный и музейный комплекс на острове Октябрьский, Калининград
Partially operationalNo update 90+ days
Original deadline
Dec 2023
Current deadline
2026
+3 yrs
Latest · 28 May 2026Stroytransgaz reported on 28 May 2026 that commissioning of the automated scenery storage system of the production and storage complex has started (120 conveyors tested); at end-April the Bolshoi branch was 76.75% ready, the 'Gipar' cantilever 75% mounted and the production complex 80% built. (Stroytransgaz (general contractor, Telegram))
Full record

Project

Presidential cultural cluster of 14 objects on Oktyabrsky island: Tretyakov Gallery branch (opened 12 June 2025, 14 exhibition halls), choreography academy, music school and RGISI branch are in operation; under construction are the Bolshoi Theatre branch (Snøhetta design, cantilever 'Gipar', glazed facade of about 1,700 m²) and its production and storage complex.

Next milestone

Completion of the Bolshoi Theatre branch and the production and storage complex

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Construction of Vokzalnaya station, Krasnoyarsk (June 2025)Photo: MBH / Wikimedia Commons, CC BY 4.033%TransportUpdated 28 Oct 2026
Krasnoyarsk Krai

Krasnoyarsk metrotram (light metro), first stage

Линия скоростного метротрамвая в Красноярске (первый этап)
Under constructionDelayed > 12 months
Original deadline
2025
Current deadline
2028
+3 yrs
Latest · 28 Oct 2026On 28 Oct 2026 Deputy PM Khusnullin inspected the site: 50% of all underground tunnelling is done (more than 10 km of tunnels), five tunnel boring machines are working simultaneously, and construction and installation works are to be completed by the end of 2028. (Marat Khusnullin, Deputy Prime Minister (Telegram))
Full record

Project

First stage of an underground/surface light-rail line in Krasnoyarsk with six stations: five underground (Vysotnaya, Ulitsa Kopylova, Vokzalnaya, Ploshchad Revolyutsii, Ulitsa Karla Marksa) and one at surface level (Ulitsa Shakhterov), each with a 60 m platform. Deputy PM Khusnullin puts the total length at more than 23 km.

Next milestone

Tunnel boring machine «Anastasia» is to reach the future Vokzalnaya station (about 500 m remaining as of 9 Oct 2026) and will then be relocated to continue towards Ulitsa Kopylova.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Murmansk Oblast

Lavna coal terminal, Murmansk Transport Hub

Комплекс перегрузки угля «Лавна» (Мурманский транспортный узел)
Partially operationalDelayed > 12 months
Construction progress12 of 18 Mt/yr capacity installed
Original deadline
Dec 2024
Current deadline
2027
+3 yrs
Latest · 1 Oct 2026On 1 October 2026 Murmansk governor Andrei Chibis said the first stage of the Murmansk Transport Hub is practically complete, with almost 50 km of railway built and the Lavna port in operation; the next step is raising the hub's capacity to 45 Mt. (Governor Andrei Chibis (Telegram))
Full record

Project

Deep-water, ice-free coal terminal on the western shore of the Kola Bay with a design capacity of 18 Mt per year, served by a new 49.7 km railway Vykhodnoy–Lavna with a bridge over the Tuloma river. Rail traffic started in December 2023, coal shipments in March 2025.

Next milestone

Commissioning of the remaining process lines and two coal yards, bringing capacity towards the design 18 Mt per year. (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Republic of Sakha (Yakutia)

Lena Bridge near Yakutsk

Мост через реку Лену в районе Якутска (Ленский мост)
Under constructionDelayed > 12 months
Construction progress357 of 920 bored piles installed
as of 9 Oct 2026 · VIS Group (general contractor)
Original deadline
2025
Current deadline
2028
+3 yrs
Latest · 9 Oct 2026On 9 October 2026 general contractor VIS Group reported 357 of 920 bored piles completed for the bridge's 26 piers (49 in the central and 8 in the right pylon cofferdam) and over a quarter of the right-bank approach embankment placed; work in the river channel continues through winter. (VIS Group (general contractor))
Full record

Project

Three-pylon cable-stayed road bridge, 4.6 km long (2.5 km cable-stayed section), with a central pylon 284.5 m high, on permafrost near Staraya Tabaga, about 30 km upstream of Yakutsk. Including approaches the new road is 14.5 km long and will link the Lena and Kolyma federal highways with the Vilyuy highway, replacing ferry crossings; two lanes, up to 5,300 vehicles per day.

Next milestone

Pile foundations for the central (No. 9) and right pylons inside the river cofferdams; work around the central cofferdam continues through winter 2026/27 under an insulated enclosure.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Primorsky Krai

Museum, Theatre and Educational Complex on Eagle's Nest Hill (Orlinoe Gnezdo), Vladivostok

Музейный и театрально-образовательный комплекс на сопке Орлиное Гнездо, Владивосток
Partially operationalDelayed > 12 months
Original deadline
Dec 2023
Current deadline
2026
+3 yrs
Latest · 9 Oct 2026On 9 October 2026 Governor Kozhemyako reported that installation of the stage machinery has started; the platforms can move scenery weighing more than 6 tonnes. (Oleg Kozhemyako, Governor (Telegram))
Full record

Project

Presidential cultural cluster of 13 objects; the educational part on Russky island (incl. choreography academy branch) is in operation. Under construction on Eagle's Nest hill: a combined building with a Mariinsky Theatre branch (opera and ballet stage of 1,450 seats per the government), a Tretyakov Gallery branch and an RGISI branch.

Next milestone

Completion of facades and stage machinery; commissioning of the theatre-museum building

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Samara Oblast

Samara metro: Teatralnaya station

Станция метро «Театральная» (Самара)
Under constructionDelayed > 12 months
Original deadline
2024
Current deadline
2027
+3 yrs
Latest · 2 Oct 2026On 2 October 2026 the regional Ministry of Construction reported that the main structures were 99% complete, engineering systems were being installed, track was being laid in the tunnels and finishing works with granite had begun. (Samara Region Ministry of Construction (Telegram))
Full record

Project

Teatralnaya, the 11th station of the Samara metro, extends the existing line from Alabinskaya into the historic centre and completes the first line; the station complex has 286 functional rooms, and the right running tunnel bored for it is more than 1,500 m long.

Next milestone

Technical test run of trains, planned for the first quarter of 2027; commissioning and opening in the second quarter of 2027. The first stage of street works near Ulitsa Polevaya is to be finished by the end of 2026.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Chechen Republic

Veduchi resort: new north-slope ski area with VL1 gondola

Курорт «Ведучи»: новая зона катания на северном склоне и канатная дорога VL1
Under constructionDelayed > 12 months
Construction progress18 of 20 objects in operation
Original deadline
2024
Current deadline
2027
+3 yrs
Latest · 24 Sep 2026On 24 September 2026 Deputy Economy Minister Sergey Nazarov inspected the site. Kavkaz.RF CEO Yumshanov reported 18 of 20 objects in operation; the full launch of the north slope now depends on the VL1 gondola (planned for 2027) and the snowmaking system (95% ready, planned for end-2026). (Kavkaz.RF (Telegram), statement by CEO Andrey Yumshanov)
Full record

Project

Kavkaz.RF is building the main ski area of the Veduchi resort on the north slope of the Daneduk ridge: new cable cars and pistes, a snowmaking system and the VL1 gondola, a 4.3 km link across the Argun gorge on only three towers with a span of about 3 km. By September 2026, 18 of 20 infrastructure objects were in operation.

Next milestone

Launch of the snowmaking system (95% ready) before the end of 2026; VL1 rope pulling and commissioning carry over into 2027 (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Krasnoyarsk Krai (Taimyr Peninsula)

Vostok Oil: Vankor–Payakha–Bukhta Sever pipeline and oil terminal

«Восток Ойл»: нефтепровод «Ванкор – Пайяха – Бухта Север» и порт «Бухта Север»
Partially operationalDelayed > 12 months
Construction progressmore than 2,000 of 12,000 wells drilled
as of 5 Sep 2026 · kremlin.ru
Original deadline
2024
Current deadline
2027
+3 yrs
Latest · 5 Sep 2026On 5 September 2026 the trunk pipeline and the first stage of the Bukhta Sever terminal were put into operation at a ceremony with President Putin by video link; loading of the first oil into the Arctic tanker 'Valentin Pikul' began. (kremlin.ru)
Full record

Project

Arctic oil project with a 790-km trunk pipeline from the Vankor and Payakha fields to the Bukhta Sever terminal on the Yenisei Gulf (design capacity 100 Mt/yr; 414 km twin-line). The first stage of the terminal handles 30 Mt/yr.

Next milestone

Shipments of 30 million tonnes of oil to consumers in the second half of 2027; up to 50 million tonnes by 2030. (Dec 2027)

Deadline history

Amur Oblast (near Svobodny)

Amur Gas Chemical Complex

Амурский газохимический комплекс (АГХК)
Under constructionDelayed > 12 months
Original deadline
2025
Current deadline
2027
+2 yrs
Latest · 1 Sep 2026On 1 September 2026 Amur Governor Vasily Orlov said the launch had slipped because of longer commissioning works; a fire on 25 August 2026 at an auxiliary section of the pyrolysis unit had halted commissioning, while works on unaffected facilities continued. (Governor Vasily Orlov, quoted by InvestFuture)
Full record

Project

Polymer plant near Svobodny designed to produce 2.7 million t/yr of polyethylene and polypropylene from ethane and LPG supplied by Gazprom's neighbouring Amur gas processing plant. Commissioning works began in 2026.

Next milestone

First polyethylene output; no new date has been given since the August 2026 fire.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Sakhalin Oblast

Gorny Vozdukh ski resort expansion, Yuzhno-Sakhalinsk

Развитие курорта «Горный воздух», Южно-Сахалинск
Under constructionDelayed > 12 months
Construction progress40 of 90 km of pistes
Original deadline
2026
Current deadline
2028
+2 yrs
Latest · 25 Sep 2026On 25 September 2026 Governor Limarenko reported to a meeting on Far East tourism chaired by presidential envoy Trutnev that construction of the new Krasnaya–Yug cable car began this year, an Ostraya–Sever line is being designed and pistes are to be extended to 90 km. On 1 August 2026 he said concreting of the two five-star hotels was nearly finished. (Valery Limarenko, Governor of Sakhalin Oblast (Telegram))
Full record

Project

Expansion of the ski resort inside the city of Yuzhno-Sakhalinsk: two five-star hotels with 310 and 575 rooms on the lower and middle stations, a new Krasnaya–Yug cable car towards the valley between Krasnaya and Ostraya mountains as a first step to the all-season 'Ayna Valley' area, and growth of the piste network from about 40 km to 90 km.

Next milestone

5 km of new pistes in 2026; snowmaking on the Kedrovaya and Taezhnaya pistes is being installed; piste network to reach 90 km by 2029 (2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Moscow, Moscow Oblast, Tver, Novgorod and Leningrad Oblasts, St Petersburg

High-speed railway Moscow–St Petersburg (VSM-1)

Высокоскоростная магистраль Москва – Санкт-Петербург (ВСМ)
Under constructionDelayed > 12 months
Construction progressNo official progress figure
Original deadline
2026
Current deadline
2028
+2 yrs
Latest · 23 Oct 2026At a meeting chaired by Deputy PM Andrei Nikitin on 23 October 2026, the workforce on the line was put at 32,000 people and 11,000 machines; a test centre for high-speed trains has been commissioned, and production of the first two trains is under way in parallel at Ural Locomotives. (Ministry of Transport (Telegram))
Full record

Project

Russia's first high-speed line, about 700 km long, designed for trains running at up to 400 km/h. The project comprises seven construction stages and 239 bridges and viaducts with a total length of 180 km; the 129 km Kryukovo–Novaya Tver section (stages 6 and 7) is being built first as a test track.

Next milestone

Start of testing of the first two Russian-built high-speed trains on the Zelenograd (Kryukovo)–Tver test section. (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Khabarovsk Krai

Khabarovsk CHP-4 (South CHP)

Хабаровская ТЭЦ-4 (Южная ТЭЦ)
Partially operationalDelayed > 12 months
Construction progressNo official progress figure
Original deadline
2025
Current deadline
2027
+2 yrs
Latest · 15 Oct 2026On 15 October 2026 RusHydro reported that 1,080 Gcal/h of heat capacity was put into service in the first half of 2026 as part of the second construction stage of the South CHP (Khabarovsk CHP-4). The second of the two gas turbines left the factory on 1 June 2026. (RusHydro (Telegram): board of directors decisions, report on the first half of 2026)
Full record

Project

New gas-fired combined-cycle heat and power plant in Khabarovsk with a design capacity of 410 MW and 1,389 Gcal/h, built to replace the 70-year-old Khabarovsk CHP-1. Six hot-water boilers with 1,080 Gcal/h were put into service in the first half of 2026; the main building and the two gas-turbine units are still under construction.

Next milestone

Completion and commissioning of the combined-cycle units, planned by RusHydro for mid-2027 provided equipment is delivered on time. (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Kursk Oblast

Kursk Nuclear Power Plant II

Курская АЭС-2
Partially operationalDelayed > 12 months
Construction progress1 of 4 power units in operation
as of 29 Apr 2026 · Rosatom (Telegram)
Original deadline
2025
Current deadline
2027
+2 yrs
Latest · 20 Aug 2026On 20 August 2026 Rosatom head Alexei Likhachev told a Kremlin meeting that the first VVER-TOI unit at Kursk had generated more than 4 billion kWh and, at 1,250 MW, is the most powerful unit in Russia. (kremlin.ru, meeting on nuclear energy development)
Full record

Project

Replacement nuclear power plant at Kurchatov with VVER-TOI reactor units of about 1,250 MW each. Unit 1 (1,253 MW) entered commercial operation in April 2026; unit 2 is under construction, unit 3 is in early construction and unit 4 holds a siting licence.

Next milestone

Start-up of unit 2 (first two units to be in service by 2027, according to Deputy PM Novak). (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Olimpiyskiy complex before the reconstruction (2004)Photo: Artyom Svetlov / Wikimedia Commons, CC BY 4.080%Cities & SportUpdated 27 Oct 2026
Moscow

Olimpiyskiy sports and concert complex reconstruction (Moscow)

Реконструкция спорткомплекса «Олимпийский» (Москва)
Under constructionDelayed > 12 months
Construction progress80%
Original deadline
2025
Current deadline
2027
+2 yrs
Latest · 27 Oct 2026On 27 Oct 2026 Mayor Sobyanin put construction readiness at about 80%, with more than 5,500 workers on site and a total building volume of about 6.5 million m³. (Sergei Sobyanin, Mayor of Moscow (Telegram))
Full record

Project

Complete rebuild of the 1980 Olympic arena on Olimpiysky Prospekt into a multifunctional complex of four buildings: a main building with a 12,000-seat concert hall at 50 m height and a 1 km elevated running track, an aquatics centre with 15 pools, a sports and fitness centre with ice rinks, and a small concert hall. More than 100 sports venues for over 40 sports are planned.

Next milestone

Completion of the main construction works on the complex, planned for 2027; the new Dostoevskaya station on the Koltsevaya line is being built in parallel to serve the site.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Sakha Republic (Yakutia)

Yakutsk GRES-2, stage 2 (Tuymaada thermal power plant)

Якутская ГРЭС-2, вторая очередь (ТЭС «Туймаада»)
Under constructionNo update 90+ days
Construction progressNo official progress figure
Original deadline
2025
Current deadline
2027
+2 yrs
Latest · 16 Mar 2026On 16 March 2026 RusHydro reported that the generator of the first turbine had been placed on its foundation in the main building; more than 1,700 workers and 50 machines were on site. (RusHydro (Telegram): generator of the first turbine installed)
Full record

Project

Second stage of Yakutsk GRES-2, now named Tuymaada thermal power plant: a gas-fired plant on permafrost with two 80 MW power units, 160 MW electric and 280 Gcal/h heat capacity in total. Together with stage 1 (in service since 2017) it is to replace the old Yakutsk GRES, which will then be shut down.

Next milestone

Completion of construction, which RusHydro expects in 2027 (the Head of Yakutia spoke of phased commissioning by 2028). (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Komsomolsk-on-Amur, station square (2015)Photo: Andshel / Wikimedia Commons, CC BY-SA 4.080%Cities & SportUpdated 26 Oct 2026
Khabarovsk Krai

Avangard stadium reconstruction (Komsomolsk-on-Amur)

Реконструкция стадиона «Авангард» (Комсомольск-на-Амуре)
Under constructionDelayed > 12 months
Original deadline
2024
Current deadline
Oct 2026
+22 mo
Latest · 26 Oct 2026On 26 Oct 2026 Governor Demeshin said the reconstruction is still not complete: the artificial turf is laid and the seats are installed, the grounds are partly landscaped, but the rubber surface of the running tracks has not been laid; readiness is 80%. (Dmitry Demeshin, Governor of Khabarovsk Krai (Telegram))
Full record

Project

Reconstruction of the city's main stadium, closed for works since 2021: an artificial-turf football pitch, running tracks, floodlight masts, renovated rooms under the stands and more than 6,000 new seats. The governor lists completion of the stadium's second stage among the projects of the Komsomolsk-on-Amur master plan.

Next milestone

Laying of the rubber surface on the running tracks, which according to Governor Demeshin cannot be done properly once the cold sets in; no new completion date had been announced as of 26 Oct 2026.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Moscow

Torpedo (Eduard Streltsov) stadium reconstruction (Moscow)

Реконструкция стадиона «Торпедо» им. Эдуарда Стрельцова (Москва)
CompletedDelayed > 12 months
Original deadline
2024
Current deadline
Sep 2026
+21 mo
Latest · 5 Sep 2026On 5 Sep 2026 (Moscow City Day) President Putin and Mayor Sobyanin opened the reconstructed stadium with 15,000 seats and three adjacent training pitches. (Sergei Sobyanin, Mayor of Moscow (Telegram))
Full record

Project

Rebuild of the 1959 Torpedo stadium on Vostochnaya Street (former ZIL area) into a 15,000-seat football stadium (up to 20,000 in concert mode) with a FIFA Quality Pro pitch, a cantilevered roof of almost 19 m and three training pitches.

Deadline history

Primorsky Krai

Arsenyev year-round family ski resort, Primorye

Горнолыжный круглогодичный семейный курорт «Арсеньев», Приморье
Partially operationalNo update 90+ days
Construction progressNo official progress figure
Original deadline
2025
Current deadline
Dec 2026
+1 yr
Latest · 7 Jul 2026On 7 July 2026 Governor Kozhemyako reported that test interior fit-out has started in the resort's apart-hotels, which are to receive guests next season; landscaping is under way. (Oleg Kozhemyako, Governor (Telegram))
Full record

Project

Ski resort on Obzornaya hill in Arsenyev: 12 km of slopes with artificial snowmaking, two high-speed chairlifts (1,570 m and 1,522 m), about 230 hotel rooms, capacity up to 2,700 skiers a day, plus an all-season water and spa complex.

Next milestone

Full launch for the 2026/27 season: apart-hotels, new slopes (12 km in total), restaurants; water and spa complex during the season (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Primorsky Krai

Artyom CHP-2 (Shkotovo CHP)

Артёмовская ТЭЦ-2 (Шкотовская ТЭЦ)
Under constructionDelayed ≤ 12 months
Construction progress67%
Original deadline
2026
Current deadline
2027
+1 yr
Latest · 14 Sep 2026On 14 September 2026 RusHydro reported the start of commissioning works on the hot-water boilers after gas began to flow through the first distribution line from the Artyom-2 gas distribution station. (RusHydro (Telegram))
Full record

Project

Gas-fired combined-cycle heat and power plant with 440 MW electrical and 456 Gcal/h thermal capacity (two CCGT units and three hot-water boilers). It is to replace the coal-fired Artyom CHP built in 1936.

Next milestone

Start of testing of the generating equipment and completion of the second (back-up) gas supply line, planned for November 2026. (Nov 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Kaliningrad Oblast

Kantiana campus of the Immanuel Kant Baltic Federal University

Кампус «Кантиана» Балтийского федерального университета имени И. Канта
Partially operationalDelayed ≤ 12 months
Original deadline
2025
Current deadline
Dec 2026
+1 yr
Latest · 20 Oct 2026On 20 Oct 2026 Deputy PM Khusnullin reported that construction of the Institute of High Technologies building is complete and a certificate of compliance has been issued; the state client put overall readiness at about 95%. (Marat Khusnullin, Deputy Prime Minister (Telegram))
Full record

Project

New university campus of the Baltic Federal University in Kaliningrad, built under the federal programme for a network of modern campuses: teaching and research buildings (three «Biomed» buildings, Institute of High Technologies, Higher School of Philosophy and Social Sciences), a conference complex and two dormitories with almost 2,500 places. The state client puts the total floor area at more than 115,000 m².

Next milestone

Completion of the last two buildings — the Higher School of Philosophy and Social Sciences (with the clock tower) and the conference complex — by the end of 2026; according to the university, the campus is to be fully in use from September 2027. (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Sverdlovsk Oblast / Tyumen Oblast

M-12 'Vostok' extension Yekaterinburg–Tyumen (R-351 upgrade)

Продление М-12 «Восток» до Тюмени (реконструкция Р-351 Екатеринбург – Тюмень)
Under constructionDelayed ≤ 12 months
Construction progressNo official progress figure
Original deadline
2025
Current deadline
Dec 2026
+1 yr
Latest · 29 Oct 2026On 29 October 2026 Rosavtodor said four-lane traffic along the full length of the R-351 is planned to open before the end of the year, after which the road becomes part of M-12. (Rosavtodor (Telegram))
Full record

Project

Widening of the federal R-351 Yekaterinburg–Tyumen highway to four lanes along its full length, including a 17 km bypass of Bogdanovich (opened 2025) and a new bypass of Beloyarsky, Mezenskoye and Maly Brusyany (km 35–89). The upgraded road is to become part of the M-12 'Vostok' expressway, giving a continuous high-speed route Moscow–Tyumen.

Next milestone

Opening of four-lane traffic along the entire R-351; the road then becomes part of M-12 (Khusnullin: 'by November'; Rosavtodor: 'by the end of the year'). (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Saratov Oblast

Southern bypass of Saratov with new Volga bridge

Южный обход Саратова с мостовым переходом через Волгу
Under constructionNo update 90+ days
Construction progressNo official progress figure
Original deadline
2027
Current deadline
2028
+1 yr
Latest · 29 Jul 2026On 29 July 2026 Rosavtodor said construction of the 63 km Southern bypass with the new Volga bridge was continuing and that completion is scheduled for 2028. (Rosavtodor (Telegram))
Full record

Project

A 63 km southern bypass of the Saratov–Engels agglomeration that will link several federal highways and close the Saratov ring road. Its core is a four-lane Volga crossing more than 14 km long including approaches (11.8 km over water), with two floodplain bridges and a 2,084.4 m cable-stayed channel bridge with a 152 m pylon; it will be the city's third road crossing of the Volga.

Next milestone

Completion of the Volga bridge crossing: after the span launching started in June 2026, works on the crossing are to be finished in December 2027 (Volodin); the full bypass follows in 2028. (Dec 2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Primorsky Krai

'Primorye' year-round seaside resort, Aleut Bay (Khasan district)

Круглогодичный морской курорт «Приморье», бухта Алеут (Хасанский округ)
DesignNo update 90+ days
Construction progressNo official progress figure
Original deadline
2028
Current deadline
2028
On time
Latest · 10 Apr 2026At a meeting chaired by Presidential Envoy Trutnev in April 2026, projects for grid infrastructure for the resort were presented, including a 220 kV line with a substation (Governor Kozhemyako, 10 April 2026). (Oleg Kozhemyako, Governor (Telegram))
Full record

Project

Federal 'Five Seas and Lake Baikal' resort on more than 200 ha at Aleut Bay: about 3,800 rooms, aquapark with heated outdoor pools, bath complexes, water sports school, medical centre, arena and fish market; requires a new 220 kV line with substation and road, water and sewage upgrades in the Khasan district.

Next milestone

Decision on 220 kV power line and substation for the resort and the Khasan district

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Siberia and Russian Far East (Buryatia, Zabaykalsky Krai, Amur Oblast, Khabarovsk Krai and others)

Eastern Polygon stage 3: BAM and Trans-Siberian capacity expansion

Третий этап модернизации Восточного полигона (БАМ и Транссиб)
Under constructionOn schedule
Construction progressNo official progress figure
Original deadline
2035
Current deadline
2035
On time
Latest · 2 Sep 2026On 2 September 2026 President Putin, via video link from the Eastern Economic Forum, gave the start to boring of the second Severomuysky tunnel (over 15 km); four tunnel boring machines have been installed at the eastern and western portals. (Kremlin / Ministry of Transport (Telegram))
Full record

Project

Third stage of the expansion of the Baikal–Amur Mainline and the Trans-Siberian Railway, aiming to raise eastbound carrying capacity from 180 Mt (2024) to 210 Mt in 2030 and 270 Mt in 2032. Key structures are the second Severomuysky tunnel (over 15 km), second Kodarsky and Kuznetsovsky tunnels and a second rail bridge over the Amur, plus track doubling and electrification.

Next milestone

Opening of electric traction on the Volochayevka-2–Komsomolsk-on-Amur section (2026); electrification to reach Vanino in 2027. (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Kabardino-Balkar Republic

Elbrus resort: eastern sector ski area

Курорт «Эльбрус»: новая зона катания в восточном секторе
Partially operationalOn schedule
Construction progressNo official progress figure
Original deadline
2028
Current deadline
Dec 2028
On time
Latest · 7 Oct 2026On 7 October 2026 Kavkaz.RF announced that the 2026/27 season will offer 23 km of pistes and five cable cars, including the new eastern-sector zone; a panoramic restaurant overlooking the Terskol Peak observatory is planned in the new zone. In July 2026 Deputy Minister Nazarov had inspected the summer building season; the eight new pistes received a positive Glavgosexpertiza opinion at the end of May 2026. (Kavkaz.RF (Telegram))
Full record

Project

Eastward expansion of the Elbrus ski resort towards the Terskol Peak observatory at 3,300–3,500 m. A first stage with two cable cars (a chairlift and a gondola) and 5.2 km of pistes opened in December 2025; the second stage foresees four more cable cars and 12 km of new pistes on eight runs.

Next milestone

Commissioning of a panoramic restaurant at the new EL6 gondola and of a piste-machine garage in 2026; environmental review and building permit for the eight new pistes (2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Leningrad Oblast (Sosnovy Bor)

Leningrad Nuclear Power Plant II, units 3 and 4 (Leningrad NPP units 7 and 8)

Ленинградская АЭС-2, энергоблоки № 3 и № 4 (энергоблоки № 7 и № 8 ЛАЭС)
Under constructionOn schedule
Construction progressNo official progress figure
Original deadline
2032
Current deadline
2032
On time
Latest · 22 Oct 2026On 22 October 2026 Rosatom reported that the service platform (78 t) and cantilever truss (148 t) of the core catcher had been installed in the reactor shaft of unit 4; the turbine building foundation of unit 3 received its first concrete on 9 September 2026. (Rosatom (Telegram))
Full record

Project

Two VVER-1200 reactor units at Sosnovy Bor that are to replace the remaining RBMK-1000 units of the Leningrad NPP. Rosatom plans commissioning in 2030 (unit 3) and 2032 (unit 4).

Next milestone

Installation of the reactor pressure vessel at unit 3, planned for 2027 (unit 4: 2029). (2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Krasnoyarsk Krai

Norilsk renovation (comprehensive development plan to 2035)

Реновация Норильска (комплексный план социально-экономического развития до 2035 года)
Under constructionOn schedule
Construction progressNo official progress figure
Original deadline
2035
Current deadline
2035
On time
Latest · 24 Sep 2026On 24 Sep 2026 Nornickel reported that the new multi-specialty polyclinic in Talnakh (up to 1,000 visits per shift) had reached its seventh, technical floor; the thermal envelope is to be closed before winter and completion is planned for 2028. (Nornickel (official Telegram))
Full record

Project

Federal-regional-municipal-corporate plan approved by the government in December 2021 to renew the Arctic city of Norilsk by 2035: more than 70 new apartment buildings, demolition of more than 40 unsafe buildings, plus new and renovated social facilities, utilities and public spaces.

Next milestone

Three more apartment buildings under construction (four more planned by 2028); renovation of Zapolyarny State University due in 2027; new Talnakh polyclinic due in 2028.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Primorsky Krai

Partizanskaya GRES expansion (two new power units)

Расширение Партизанской ГРЭС (два новых энергоблока)
Under constructionNo update 90+ days
Original deadline
2026
Current deadline
Dec 2026
On time
Latest · 8 Apr 2026On 8 April 2026 RusHydro reported, during an inspection by Deputy PM Yuri Trutnev, that the project was 72% complete: the main building is under construction, two boilers and turbine unit No. 1 are being installed, and 4 of 5 power transformers are in place. (RusHydro (Telegram): Trutnev inspects Shkotovo CHP and Partizanskaya GRES)
Full record

Project

Two new coal-fired power units with 280 MW in total at Partizanskaya GRES, built as a separate plant with its own fuel supply and water supply. They are to power railway traction substations on the Trans-Siberian Railway; station capacity will rise to 480 MW.

Next milestone

Completion of both power units, planned by RusHydro by the end of 2026. (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Perm Krai

Perm Arena multifunctional sports arena (Perm)

Многофункциональная спортивная арена «Пермь Арена» (Пермь)
Under constructionOn schedule
Construction progress50%
Original deadline
2027
Current deadline
2027
On time
Latest · 6 Oct 2026On 6 Oct 2026 Governor Makhonin reported that main works on the frame, roof and outer envelope are being completed while engineering systems and interior structures are installed; the first section of the decorative facade was mounted in September. (Dmitry Makhonin, Governor of Perm Krai (Telegram))
Full record

Project

New multifunctional arena on Lokomotivnaya Street with 10,500 seats, two ice surfaces and almost 90,000 m² of floor space (governor, Aug 2026), height over 45 m, for competitions, concerts and business events.

Next milestone

Closing the thermal envelope and starting heating in autumn 2026 so that interior finishing can proceed over the winter; the arena is to host events of the All-Russian Winter Spartakiad in 2028.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Smolensk Oblast

Smolensk Nuclear Power Plant II

Смоленская АЭС-2
Under constructionOn schedule
Construction progressNo official progress figure
Original deadline
2035
Current deadline
2035
On time
Latest · 22 Oct 2026On 22 October 2026 Rosatom reported that deliveries had begun for the modular building of the transformer substation that will supply the construction base; a reinforcement shop, roads, utility networks and the foundations of the concrete plant are being built. (Rosatom (Telegram): preparations for the construction-base substation)
Full record

Project

Replacement nuclear power plant near Desnogorsk with two VVER-TOI units (2,400 MW in total in the 2017 general scheme) to take over from the RBMK units of the existing Smolensk NPP. The project is in its preparatory phase: the construction and installation base is being built; first concrete for unit 1 is planned for 2027.

Next milestone

Start of the main construction period in March 2027, with first concrete for the reactor building foundation of unit 1. (Mar 2027)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Republic of Buryatia

Ulan-Ude master plan: renewal of the city centre

Мастер-план Улан-Удэ: обновление центральной части города
Under constructionOn schedule
Construction progressNo official progress figure
Original deadline
2030
Current deadline
2030
On time
Latest · 11 Sep 2026On 11 Sep 2026 Head of Buryatia Alexei Tsydenov reported that the new central substation, which supplies the theatre, museum, campus, school and the housing project of more than 200,000 m², had been energised; the theatre, museum, campus and school were still under construction. (Alexei Tsydenov, Head of Buryatia (Telegram))
Full record

Project

Comprehensive development plan for Ulan-Ude to 2030 (approved by government order in 2023), built around a new centre: integrated redevelopment with about 197,000 m² of housing, a 760-place school, the Baikal theatre (halls for 1,000 and 300), a National Museum, an inter-university campus, a new substation and seven road overpasses.

Next milestone

Completion of the National Museum, scheduled for 2026; the Baikal theatre is due in Q1 2027. (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Republic of Buryatia

'Magic Baikal' year-round resort, Baikalskaya Gavan SEZ (Buryatia)

Круглогодичный курорт «Волшебный Байкал», ОЭЗ «Байкальская гавань» (Бурятия)
Under constructionNo update 90+ days
Construction progressNo official progress figure
Original deadline
–
Current deadline
2032
Latest · 3 Jun 2026On 3 June 2026 Head of Buryatia Tsydenov reported to the government subcommission that the resort has moved into construction: the first hotel with 153 rooms is being built. (Alexei Tsydenov, Head of Buryatia (Telegram))
Full record

Project

Resort on the eastern shore of Lake Baikal (sites Turka, Peski, Goryachinsk, Bukhta Bezymyannaya) within the federal project 'Five Seas and Lake Baikal'; eight investors plan about 5,000 hotel rooms, the state funds power, water and sewage infrastructure.

Next milestone

Completion of the first hotel (153 rooms); new substations and treatment plants (design stage)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Krasnodar Krai (Sochi)

Adler bypass (Sochi)

Автомобильная дорога «Обход Адлера»
Under constructionNo official deadline
Construction progressNo official progress figure
Original deadline
2026
Current deadline
–
Latest · 22 Sep 2026On 22 September 2026 Avtodor reported that the first span of the bridge crossings over the Kudepsta river had been concreted on the western side, using 1,300 m³ of concrete. (Avtodor (Telegram))
Full record

Project

New road of about 8 km from Kudepsta to Vysokoye that takes transit traffic between Sochi, the airport and Krasnaya Polyana out of Adler; about 6 km of it runs in twin tunnels of 5,878 m and 5,894 m with two lanes each, which will be Russia's longest road tunnels, plus a 916 m viaduct along the Kudepsta river. It is to become part of a planned expressway from the M-4 Don to Sochi.

Next milestone

Start of tunnel boring from the eastern portal at Vysokoye; in May 2026 Avtodor reported that concreting of the launch cradles for the tunnel boring machines was being completed.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Kaliningrad Oblast (Neman district)

Baltic Nuclear Power Plant

Балтийская АЭС
FrozenFrozen
Construction progressNo official progress figure
Original deadline
–
Current deadline
–
Latest · 3 May 2025In May 2025 Rosatom head Alexei Likhachev said the company regards the Baltic NPP as postponed and is waiting for economic and political conditions to return to it; whether a small or large plant would be built is still to be decided. (Rosatom head Alexei Likhachev, quoted by TASS via Kaliningrad.Ru/News Mail – media_quoting_official)
Full record

Project

Two-unit nuclear power plant project with VVER-1200 reactors near Neman, Kaliningrad region. Rosatom considers the project postponed; the future plant format (large or small reactors) is open.

Next milestone

Decision on whether and in what format to resume the project; no date announced.

Amur Oblast, Jewish Autonomous Oblast, Khabarovsk Krai

Belogorsk–Khabarovsk gas pipeline

Газопровод «Белогорск – Хабаровск»
Under constructionNo official deadline
Construction progress95%
Original deadline
–
Current deadline
2026
Latest · 29 Oct 2026On 29 October 2026 Gazprom reported construction readiness of 95% and said the pipeline has been tied in to both the Sakhalin–Khabarovsk–Vladivostok and Power of Siberia systems. (Gazprom (Telegram))
Full record

Project

828-km trunk gas pipeline connecting the Power of Siberia pipeline with the Sakhalin–Khabarovsk–Vladivostok system; first stage of Gazprom's Eastern Gas Supply System. It includes crossings of the Zeya, Bureya and Amur rivers.

Next milestone

Commissioning, which Gazprom CEO Miller announced for 2026. (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Republic of Dagestan

Caspian Coastal Cluster seaside resort, Dagestan

Курорт «Каспийский прибрежный кластер», Дагестан
Under constructionNo official deadline
Construction progressNo official progress figure
Original deadline
–
Current deadline
Dec 2027
Latest · 25 Sep 2026On 25 September 2026 Kavkaz.RF reported to Deputy Economy Minister Nazarov that construction is under way on 5 of the 6 first-stage objects with positive state expertise; all six are to be commissioned in December 2027. Three access roads are also being built. (Kavkaz.RF (Telegram))
Full record

Project

Year-round seaside resort in a special economic zone on the Caspian coast near Kaspiysk, part of the federal project 'Five Seas and Lake Baikal'. The state builds 7 first-stage infrastructure objects (4-storey multifunctional centre of 7,500 m², 15 km of internal roads, 693-space parking, utility networks, landscaping); resort residents plan almost 3,500 hotel rooms.

Next milestone

Close the external envelope of the multifunctional centre and finish rough works; complete reinforced-concrete works on the parking garage (Dec 2026)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Perm Krai

Interuniversity campus «Budushcheye Parmy» (Future of Parma), Perm

Межвузовский кампус «Будущее Пармы», Пермь
Under constructionNo official deadline
Original deadline
–
Current deadline
–
Latest · 6 Oct 2026On 22 Sep 2026 the Perm Krai Government reported construction readiness of 27.73%, with about 1,000 workers on site daily; on 6 Oct 2026 Governor Makhonin briefed Deputy PM Chernyshenko on the continuing construction of the campus of more than 160,000 m². (Dmitry Makhonin, Governor of Perm Krai (Telegram))
Full record

Project

Campus for eight universities of Perm Krai on a 21.5 ha site on the right bank of the Kama: nine buildings with about 161,500 m² in total, including a teaching and laboratory building with technopark, five dormitories for 4,760 students, hotel buildings for teachers (329 places), a sports complex with swimming pool and a congress hall.

Next milestone

Utility networks, closing of the thermal envelope and internal walls of all buildings; Governor Makhonin says interior finishing and fitting-out of the campus will start in 2027. (2027)

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Leningrad Oblast

KAD-2 second ring road around St Petersburg (Avtodor section M-11 – Matoksa)

Вторая кольцевая автодорога вокруг Санкт-Петербурга (КАД-2), участок «Автодора» от М-11 до дороги Санкт-Петербург – Матокса
DesignNo official deadline
Construction progressNo official progress figure
Original deadline
–
Current deadline
–
Latest · 2 Oct 2026On 2 October 2026 Avtodor and the Transport Ministry reported that Glavgosexpertiza had issued a positive conclusion for the preparatory stage of the 62 km section from M-11 to the Road of Life, and that site preparation is starting. (Avtodor (Telegram))
Full record

Project

Four-lane expressway forming an outer ring around St Petersburg; the 80 km section built by Avtodor runs from the M-11 'Neva' to the St Petersburg–Matoksa road with 7 interchanges and 42 structures, including a 1.27 km cable-stayed bridge over the Neva. The first stage is the 62 km stretch from M-11 to the 'Road of Life'.

Next milestone

Site preparation for the first stage (M-11 – Road of Life, 62 km): soil replacement, relocation of utilities, archaeological and demining surveys.

Republic of North Ossetia–Alania

Mamison all-season mountain resort

Всесезонный горный курорт «Мамисон»
Partially operationalNo official deadline
Original deadline
–
Current deadline
–
Latest · 20 Oct 2026On 20 October 2026 Deputy Economy Minister Sergey Nazarov visited Mamison. Kavkaz.RF reported more than 20 km of pistes and two cable cars in operation, a snowmaking system commissioned at the end of 2025, and an extension of the special economic zone by 233.56 ha in June 2026, with a further 184.44 ha under preparation. (Kavkaz.RF (Telegram), incl. statement by CEO Andrey Yumshanov)
Full record

Project

New mountain resort built from scratch by Kavkaz.RF in the Mamison gorge. It opened on 14 March 2025 with two cable cars rising to 2,950 m; by October 2026 more than 20 km of pistes and a snowmaking system covering over 276,000 m² were in operation. The plan foresees 43 km of pistes and 5 lifts by 2030, and later more than 100 km of pistes.

Next milestone

Start of the 2026/27 winter season with almost 700 beds. (2026)

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Moscow

Moscow Metro Biryulyovskaya line

Бирюлёвская линия Московского метрополитена
Under constructionNo official deadline
Construction progressNo official progress figure
Original deadline
–
Current deadline
2029
Latest · 25 Oct 2026On 25 October 2026 tunnelling started on the 565 m connecting branch between the Biryulyovskaya and Zamoskvoretskaya lines (TBM 'Esmina'); the first section is to be completed in 2028. (Sergei Sobyanin (Telegram))
Full record

Project

New metro line from the former ZIL industrial zone to Biryulyovo Vostochnoye and Biryulyovo Zapadnoye, 22.2 km long with 10 stations, with interchanges to the Big Circle Line, the MCC, the Troitskaya and Zamoskvoretskaya lines and the Paveletsky railway line.

Next milestone

Opening of the first section ZIL–Kuryanovo (four stations: ZIL, Ostrov Mechty, Klenovy Bulvar, Kuryanovo). (2028)

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Moscow / Moscow Oblast (Krasnogorsk)

Moscow Metro Rublyovo-Arkhangelskaya line (line 17)

Рублёво-Архангельская линия Московского метрополитена
Partially operationalNo official deadline
Construction progress5 of 10 stations open
as of 5 Sep 2026 · kremlin.ru
Original deadline
–
Current deadline
2027
Latest · 28 Oct 2026On 28 October 2026 Mayor Sergei Sobyanin confirmed that the five new stations of the second section, from Bulvar Generala Karbysheva to Novorizhskaya, are to open in 2027. (Sergei Sobyanin (Telegram))
Full record

Project

New metro line from Moscow-City to Rublyovo-Arkhangelskoye (SberCity) beyond the MKAD ring road, with 10 stations up to Novorizhskaya; a later extension towards Krasnogorsk is planned. The first section with 5 stations (Delovoy Tsentr–Bulvar Generala Karbysheva) opened on 5 September 2026.

Next milestone

Opening of the second section Bulvar Generala Karbysheva–Novorizhskaya with five new stations (incl. Lipovaya Roshcha and SberCity). (2027)

Deadline history

Western and Eastern Siberia to the Mongolian border (planned route)

Power of Siberia 2 / Power of Baikal gas pipeline

Газопровод «Сила Сибири – 2» («Сила Байкала»)
DesignNo official deadline
Construction progressNo official progress figure
Original deadline
–
Current deadline
–
Latest · 21 Oct 2026On 21 October 2026 Deputy PM Alexander Novak said Gazprom and CNPC were conducting commercial negotiations and could reach agreement by the end of the year; in September 2026 Energy Minister Sergei Tsivilev had said the project, now called 'Power of Baikal', was at the final stage before construction. (Deputy PM Alexander Novak, quoted by RIA Novosti via Reuters/The Moscow Times – media_quoting_official)
Full record

Project

Planned export gas pipeline from West Siberian fields to China via Mongolia (transit section 'Soyuz Vostok'), with a capacity of 50 bcm per year. A legally binding memorandum on construction was signed in September 2025; commercial terms are still under negotiation.

Next milestone

Commercial agreement between Gazprom and CNPC, which Deputy PM Novak hopes to see by the end of 2026. (Dec 2026)

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Nizhny Novgorod Region

Volga Arena ice palace on the Strelka (Nizhny Novgorod)

Ледовая арена на Стрелке «VOLGA Арена» (Нижний Новгород)
CompletedNo official deadline
Original deadline
–
Current deadline
Aug 2026
Latest · 28 Aug 2026The arena received its commissioning permit on 16 Aug 2026; on 28 Aug 2026 Governor Nikitin presented it to President Putin. (Gleb Nikitin, Governor (Telegram))
Full record

Project

New ice palace next to the 2018 World Cup stadium on the Strelka with a 12,000-seat main arena and two training rinks - according to the governor the only complex in Russia with three ice arenas. New home of KHL club Torpedo.

Deadline history

Site footage

Embedded content is loaded from Telegram, YouTube, Rutube or VK; your IP address is transmitted to them.

Sources

Methodology

Sources

Figures, deadlines and status come only from primary sources: the Russian government and Kremlin, ministries, Deputy Prime Minister Marat Khusnullin, regional governors, state clients and operators, contractors and public procurement records. Media reports serve as leads; a number reported only by media is not entered. Every figure is dated and linked.

Delay indicator

On scheduleDelayed ≤ 12 monthsDelayed > 12 monthsDeadline passedFrozenNo update 90+ days

Coverage

Major projects on Russia's internationally recognised territory in four sectors. New projects enter the tracker as soon as an official announcement names the project, its location and a responsible authority. Photos: Wikimedia Commons under free licences (author and licence on each image) and kremlin.ru/government.ru (CC BY 4.0); videos embedded from official channels.